WEEKLY UPDATES

Week of July 17th-22th

Site 1 (242 Broome Street)

Site 1 will have street work done by ConEd this weekend into next week on Broome Street and Ludlow Street. Deliveries will be brought to the site on Monday, July 18th and Tuesday, July 19th on Essex Street.  Fit out work for the interior of the residential building from the 3rd floor through the 11th floor is on-going. Work will occur on Saturday, July 22nd.

 

Site 2 (115 Delancey Street)

Site 2's progress will include exterior wall panel delivery and installation Monday, July 17th and Tuesday, July 18th.  Superstructure concrete will continue for the next few months.  Concrete pours will be scheduled throughout the week as needed and may occur into the evening hours as permitted. Interior mechanical, electrical and plumbing fit out will continue on the lower floors and cellar.  Concrete masonry installation will continue throughout floors 1 - 5.  Spray fire-proofing and paint will continue throughout the building.   Work will continue on Saturday, July 22nd.  

  

Site 5 (145 Clinton Street)

The upcoming week's work at Site 5 includes façade storefront and glass installation at residential lobby and Clinton Street; rebar, formwork, and concrete work on Broome Street park and 3rd floor terrace; perimeter wall finish framing, insulation, hydronic piping, and heating and air conditioning system installation. Final sheet rocking is ongoing from 3rd - 15th floors. Cabinetry installation continues on 9-11th floors. Window installation is ongoing with two weeks left. Façade metal panel installation is ongoing on 9th-10th floors, as well as scaffold removal from the 11th floor down. Elevator installation work continues for freight and service elevators. General construction work will occur on Saturday, July 22nd from 9am to 5pm.       

 

Site 6 (175 Delancey Street)

The coming week's activity at Site 6 includes storefront installation at the 1st floor. Interior framing, drywall, mechanical, electrical, and plumbing work continues from the cellar to the 14th floor.  Roofing and miscellaneous metal work will continue on the 4th and 5th floor terraces. ConEd will be working at the electrical vaults on Broome Street. Work will continue on Saturday, July 22ndfrom 9am-5pm.