WEEKLY UPDATES

Week of June 19th-24th

Site 1 (242 Broome Street)

Site 1 will have no street work for the next week. It is anticipated that Con Ed may do street work on Broome Street, date TBD. Fit out work for the interior of the residential building from the 3rd floor through the 11th floor is on-going.  A concrete pour may occur next week from inside of the site. Work will occur on Saturday, June 17th.

  

Site 2 (115 Delancey Street)

Site 2 will continue installing structural steel at the 7th floor.   Concrete pours are tentatively scheduled for Thursday, June 15th.  Spray fireproofing will continue at the 2nd through 6th floor.  Mechanical, electrical and plumbing work will continue throughout the sub-cellar, cellar and ground floors. Installation of masonry block and door frames will continue at the cellar through 2nd floor. Installation of exterior wall panels has begun and over-sized deliveries will occur sporadically throughout the week.  Deliveries may occur in the early morning hours. Flag persons will direct deliveries into the site. The hoist on Delancey Street is operational and will be jumped sporadically to keep pace with the vertical construction of the building. Back fill and waterproofing operations will continue on the south and west sides of site.   Work will continue Saturday, June 17th.   Installation of the ConEd vaults will continue throughout the week.   

 

Site 5 (145 Clinton Street)

The upcoming week's work at Site 5 includes façade precast base work around the 1st floor east facade. Storefront installation is ongoing on the north façade and residential lobby. Miscellaneous carpentry, plumbing, and electrical work is ongoing from cellar through 15th floor. Remaining sub-frame and window installation from 10th-13th floors is ongoing. Façade metal panel installation ongoing on 12th-13th floors, windows are finishing up on these floors, as well as scaffold removal at 13 floors. Elevator installation work continues for freight, service, and passenger elevators.  General construction work will occur on Saturday, June 17th from 9am to 5pm.   

 

Site 6 (175 Delancey Street)

The coming week's activity at Site 6 includes storefront installation at the 1st  floor Broome Street elevation. Interior framing, drywall, mechanical, electrical, and plumbing work continues from the cellar to the 14th floor. Roofing work will continue on the 4th and 5th floor terraces. Work will continue on Saturday, June 17th from 9am-5pm.