Weekly Construction Updates: Mar 20-25th

Posted on Mar 17, 2017
Site 1 (242 Broome Street)
The Site 1 crane is expected to return to Essex street at some point this week. A crane will be on Broome Street Monday, March 20th and Tuesday, March 21st. A concrete pour for the 15th floor is anticipated on Thursday, March 23rd. Curtainwall deliveries will occur on March 20th and Tuesday, March 21st. Flag persons will be directing pedestrians and traffic as needed. Work may continue on Saturday, March 25th.
Site 2 (115 Delancey Street)
Site 2 will continue installing structural steel at the 4th and 5th floors.  Steel deliveries will occur throughout the week sporadically. A concrete pour is tentatively scheduled for Thursday, March 23rd.   Spray fireproofing will continue in the cellar level and the mechanical, electrical and plumbing work will continue throughout the sub-cellar to ground floor.  Installation of masonry block and door frames will continue at the sub-cellar and cellar levels.   Installation of the hoist pad on Delancey Street will continue along with backfill operations.  Work will continue into Saturday, March 25th.
Site 5 (145 Clinton Street)
The upcoming week’s work at Site 5 includes façade brick work and waterproofing of the exterior walls up to the roof at “tower” and bulkhead completion, beginning work on the Grand Street side. Carpentry work includes hung ceiling framing from 11th-15th floor, sheet rocking from 8th-10th floors, and fit out of cellar retail space ongoing. Mechanical, electrical, and plumbing work continues on floors 3,7,11,12-15. Sub-frame and window installation from 3rd-12th floors is ongoing. Elevator installation work continues for retail, freight, and passenger elevators.  General construction work will occur on Saturday, March 25th  from 9am to 5pm. Street connection work will take place on Grand Street occupying one westbound lane. Sidewalk will be opened by Con Edison for electrical connection work. ConEd Flag persons will direct pedestrian and vehicular traffic.
Site 6 (175 Delancey Street)
The coming week’s activity at Site 6 includes brickwork, wash-down, and scaffold removal on the east elevation. Window installation will continue on the 8th and 9th floors. Interior framing, drywall, mechanical, electrical, and plumbing work continues from the cellar to the 14th floor. Roofing work will continue on the 4th & 5th terraces.  ConEd will continue vault work on Broome Street sidewalks within the site fence.  Work will continue on Saturday, March 25th  from 9am to 5pm.