Weekly Construction Updates: Jan 9th-14th

Posted on Jan 6, 2017
Site 1 (242 Broome Street)

Site 1 will continue pouring the 7th floor slab on Thursday, January 12th with the pump truck located on Broome Street. A crane will be located on Essex Street. Flag persons will be on Broome Street and Essex Street directing traffic and pedestrians. Work may occur on Saturday, January 14th.

 Site 2 (115 Delancey Street)
Site 2 will continue installing structural steel through the cellar and level 2 and waterproofing.  Steel deliveries will occur throughout the week. Concrete deck work is anticipated to begin on the ground level and will continue throughout the week.  Mechanical duct work and fire protection systems will begin mobilizing and installation on Monday, January 9th and continue throughout the week.  Steel erection and deck work will take place on Saturday, January 14th.
 Site 5 (145 Clinton Street)

The upcoming week’s work at Site 5 includes façade brick work and waterproofing of exterior walls up to the 11th floor, interior metal wall framing installation up to 15th floor, setting of door frames, and hung ceiling installation at 5th floor. Mechanical, electrical, and plumbing work continues from floors 3-15. Work will continue to progress this Saturday, January 14th from 9am to 5pm.

 Site 6 (175 Delancey Street)
The coming week’s activity at Site 6 includes brickwork on the 13th floor and window installation on the 2nd, 3rd, and 4th floors. Interior framing, mechanical, electrical and plumbing work continue from the cellar to the 14th floor. Work will continue on Saturday, January 14th from 9am to 5pm.