Weekly Construction Updates: Jan 16th-21st

Posted on Jan 13, 2017
Site 1 (242 Broome Street)

Site 1 will continue to receive steel deliveries on Essex Street. A concrete pour for the 8th floor is expected towards the end of the week. Curtain wall deliveries are expected on Thursday, January 19th. A crane may be delivered on Essex this week. Flag persons will direct pedestrian and vehicles. Work is anticipated for Saturday, January, 21st.

 Site 2 (115 Delancey Street)
Site 2 will continue installing structural steel through the cellar and level 3 and waterproofing.  Steel deliveries will occur on Thursday, January 19th and/or Friday, January 20th . Concrete deck and form work has begun and is anticipated to continue throughout the week.  Mechanical, electrical and plumbing have mobilized and the installation of perspective work will continue throughout the week.  Steel erection and concrete work will take place on Saturday, January 21st.
 Site 5 (145 Clinton Street)

The upcoming week’s work at Site 5 includes façade brick work and waterproofing of exterior walls up to the 12th floor, interior metal wall framing installation up to 15th floor, setting of door frames, and hung ceiling installation at 5th floor. Mechanical, electrical, and plumbing work continues from floors 3-15. Work will continue to progress this Saturday, January 21st from 9am to 5pm.

 Site 6 (175 Delancey Street)
The coming week’s activity at Site 6 includes brickwork on the 13th & 14th floors and window installation on the 2nd, 3rd, and 4th floors. Interior framing, mechanical, electrical and plumbing work continue from the cellar to the 14th floor. Work will continue on Saturday, January 21th from 9am to 5pm.