Weekly Construction Updates: Feb 27th-Mar 4th

Posted on Feb 24, 2017
Site 1 (242 Broome Street)
Site 1 will have the crane return to Essex Street this Wednesday, March 1st. A concrete pour for the 11th floor is anticipated on Monday, February 27th. Curtainwall deliveries will occur throughout the week. Pedestrian Guards will be on site at crosswalks during deliveries. Work will continue on Saturday, March 4th for hoist work. Flag persons will be directing traffic and pedestrians at all times.
Site 2 (115 Delancey Street)
Site 2 will continue installing structural steel through the ground floor and level 4.  Steel deliveries will occur on Monday, February 27th, Wednesday, March 1st and Friday, March 3rd. Concrete deck and form work on the ground floor and mezzanine level will continue.  A concrete deck pour for the first floor and/or mezzanine is tentatively scheduled for Wednesday, March 1st, Thursday, March 2nd or Friday, March 3rd.  Mechanical, electrical and plumbing will continue installation of perspective work in the sub-cellar through ground floor.  Installation of masonry block and door frames will continue in the sub-cellar.  Steel erection and concrete work will take place on Saturday, March 4th.
Site 5 (145 Clinton Street)
The upcoming week’s work at Site 5 includes façade brick work and waterproofing of exterior walls up to the 15th floor at “tower” and bulkhead completion. Carpentry work includes interior metal wall framing installation up to 15th floor, setting of door frames, and hung ceiling installation at the 14th floor, and sheet rocking from 4th-7th floors. Mechanical, electrical, and plumbing work continues from floors 3-15. Sub-frame and window installation from 3rd-7th floors is ongoing. Elevator installation work continues for retail, freight, and passenger elevators.  General construction work will occur on Saturday, March 4th  from 9am to 5pm. Street connection work will take place on Grand Street occupying one westbound traffic lane. Flag persons will direct pedestrian and vehicular traffic.
Site 6 (175 Delancey Street)
The coming week’s activity at Site 6 includes brickwork on the 13th and 14th floor east elevation. Window installation will continue on the 12th and 13th floor. Interior framing, drywall, mechanical, electrical, and plumbing work continues from the cellar to the 14th floor. Work will continue on Saturday, March 4th from 9am to 5pm.