Weekly Construction Updates: Feb 13th-18th

Posted on Feb 13, 2017
Site 1 (242 Broome Street)
Site 1 will be pouring concrete on Wednesday, February 15th. Concrete trucks will be staged on Broome Street. Our Crane will be on Essex Street all week. Curtainwall delivers will be throughout the week on Broome Street. Flag persons will be placed on Essex and Broome Street directing traffic and pedestrians. We will be working on Saturday, February 18th.
Site 2 (115 Delancey Street)
Site 2 will continue installing structural steel through the ground floor and level 4.   Steel deliveries will occur on Monday and Tuesday, February 13th and 14th and/or Friday, February 17th. Concrete deck and form work on the ground floor will continue along with the core tower from level 5 to 7. There is a concrete pour for the core level 6 to 7 anticipated on Thursday, February 16th.  Mechanical, electrical and plumbing will continue installation of perspective work in the sub-cellar through the ground floor.  Installation of masonry block and door frames will continue in the sub-cellar.  Steel erection and concrete work will take place on Saturday, February 18th.
Site 5 (145 Clinton Street)

The upcoming week’s work at Site 5 includes façade brick work and waterproofing of exterior walls up to the 13th floor weather permitting. Carpentry work includes interior metal wall framing installation up to 15th floor, setting of door frames, and hung ceiling installation at the 11th floor,  Sheet rocking at 4th floor begins. Mechanical, electrical, and plumbing work continues from floors 3-15. Sub-frame and windows installation from 3rd-5th floors is ongoing. Elevator installation work continues for retail, freight, and passenger elevators.  Work may occur on Saturday, February 18th from 9am to 5pm. UPDATE: Site 5 will be installing sewer and water utility connections on Grand Street on Saturday, February 18th. The work will take place on the westbound travel lane adjacent to the site.  Flag persons will direct pedestrian and vehicular traffic.

Site 6 (175 Delancey Street)
The coming week’s activity at Site 6 includes brickwork on the 11th & 12th floor east elevation. Brick wash-down and scaffold removal will continue at the north, south, and west elevations of the residential tower. Window installation will continue on the 14th floor. Interior framing, drywall,  mechanical, electrical, and plumbing work continues from the cellar to the 14th floor. Work will continue on Saturday, February 18th from 9am to 5pm.