Weekly Construction Updates: Dec 26th-31st

Posted on Dec 23, 2016
Site 1 (242 Broome Street)

Superstructure work continues at Site 1. A concrete pour is anticipated on Wednesday, December 28th. Flag persons will be directing pedestrians and vehicles. There will be no steel deliveries this week. No after-hours work is anticipated.

 Site 2 (115 Delancey Street)
Site 2 will continue installing structural steel through the cellar and level 1M and waterproofing.  Steel deliveries will occur on Tuesday, December 27th and throughout the next two weeks. A small concrete pour is tentatively scheduled on Thursday, December 29th.
 Site 5 (145 Clinton Street)

The upcoming week’s work at Site 5 includes façade brick work and waterproofing of exterior walls up to the 10th floor, interior metal wall framing installation up to 15th floor, setting of door frames, and hung ceiling installation ongoing at the 5th floor. Mechanical, electrical, and plumbing work continues from floors 3-15. No work is anticipated on Monday, December 26th or Saturday, December 31st.

 Site 6 (175 Delancey Street)

The coming week’s activity at Site 6 includes brickwork on the 11th and 12th floor and window installation on the 2nd, 3rd, and 4th floors. Interior framing and mechanical, electrical and plumbing work continue from the cellar to the 14th floor. There will be no work on Monday, December 26th. Work will continue on Saturday, December 31st from 9am to 5pm.