Weekly Construction Updates: April 10th-15th

Posted on Apr 3, 2017
Site 1 (242 Broome Street)
Vault excavation and installation on Broome Street is scheduled to start Monday, April 10th. Flag persons will be present as needed for pedestrian and vehicular traffic. Deliveries to the site will be on-going. Weekend work is anticipated for the Saturday, April 15th.
Site 2 (115 Delancey Street)
Site 2 will continue installing structural steel at the 5th and 6th floors.  Steel deliveries will occur throughout the week sporadically. Concrete pours are tentatively scheduled for Tuesday, April 11th and Thursday, April 13th.  Spray fireproofing will finish up in the cellar level and continue up to the ground level.  Mechanical, electrical and plumbing work will continue throughout the sub-cellar and ground floor. Installation of masonry block and door frames will continue at the cellar and ground floor. Installation of the hoist pad on Delancey Street will continue along with backfill operations.  Work will continue into Saturday, April 15th.   Service connections to the building on Essex Street will begin this weekend during the day.  The work will continue throughout the week in the evening through the early morning hours.  When work is in progress one travel lane on each side of Essex will remain open for vehicular traffic.  All lanes will re-open at 6am on weekdays.
Site 5 (145 Clinton Street)
The upcoming week’s work at Site 5 includes façade brick work, hanging of lintels, and waterproofing of the exterior walls on Grand Street side. Carpentry work includes hung ceiling framing from 11th-15th floor, sheet rocking from 8th-10th floors, lobby fit out, and fit out of cellar retail space ongoing. Mechanical, electrical, and plumbing work continues on floors 3,7,11 and 15. Gypcrete pouring on 5th-6th floors. Sub-frame and window installation from 10th-15th floors is ongoing. Elevator installation work continues for retail, freight, and passenger elevators.  General construction work will occur on Saturday, April 15th from 9am to 5pm.
 Site 6 (175 Delancey Street)
The coming week’s activity at Site 6 includes window installation on the 5th, 6th, 7th and 8th  floors. Interior framing, drywall, mechanical, electrical, and plumbing work continues from the cellar to the 14th floor. Roofing work will continue on the 4th and 5th terraces.  ConEd will continue vault work on Broome Street sidewalks within the site fence.  Work will continue on Saturday, April 15th from 9am to 5pm.