Weekly Construction Updates: Dec 5-10th

Posted on Dec 2, 2016

Site 1 (242 Broome Street) Site 1 will continue with superstructure, steel and back pouring of the foundation this week.  Deliveries will continue throughout the week with flag persons directing pedestrian and vehicular traffic as needed. UPDATE: Work will occur on Saturday, December, 10th. Site 2 (115 Delancey Street) Site 2 will continue installing structural steel at […]

Weekly Construction Updates: Nov 28-Dec 3

Posted on Nov 29, 2016

Site 1 (242 Broome Street) Site 1 will continue to pour the superstructure. The Second-floor slab is scheduled to be poured on Friday, December 2nd. Steel deliveries will continue on Essex street. Rebar and form work deliveries will be inside of the site on Ludlow and Broome Street. Concrete trucks and a concrete pump will […]

Weekly Construction Updates: Nov 21-26th

Posted on Nov 21, 2016

Site 1 (242 Broome Street) Site 1 will be pouring concrete on Saturday, November, 19th and Monday, November 21st. Flagmen as well as Pedestrian Traffic guards will be present. Deliveries of material are currently scheduled for Tuesday (11/22) and Wednesday (11/23). The site will be closed on Thursday, November 24th in observance of Thanksgiving. Site 2 […]

Weekly Construction Updates: Nov 14-19th

Posted on Nov 14, 2016

Site 1 (242 Broome Street) Site 1 will be pouring concrete on Wednesday, November, 16th. There will be daily deliveries of material to the site. Concrete trucks and a concrete pump will be staged on Broome Street. Flag persons will be directing pedestrian and vehicular traffic as needed. Site 2 (115 Delancey Street) Site 2 […]

Weekly Construction Updates: Nov 7th-12th

Posted on Nov 7, 2016

Site 1 (242 Broome Street) Steel is expected to be delivered to Site1 from Essex Street on Monday, November 7th and Thursday, November 10th. Flag persons will be present to direct pedestrian and vehicular traffic. Concrete superstructure work will begin on Broome and Ludlow Street.  Mobilization operations will begin on Monday, November 7th with the […]

Weekly Construction Updates: Oct 31st-Nov 5th

Posted on Oct 31, 2016

Site 1 (242 Broome Street) Site 1 will continue to take deliveries of steel from Essex Street on Monday, October 31st. Flag persons will be on Essex Street directing pedestrian and vehicular traffic. Installation of a sidewalk bridge will occur on Tuesday, November 1st. Pedestrians will be directed to a walkway by flag persons on Essex. No […]

Lower East Side Employment Network Job Info Event – This Wednesday, October 26th

Posted on Oct 24, 2016

Delancey Street Associates will present upcoming construction job opportunities at the Lower East Side Employment Network (LESEN) event, Job Success Starts Here.  Connect with training and employment opportunities and learn more about the services provided by our workforce partners LESEN, Workforce1, and Building Skills NY. Wednesday, October 26, 2016, 4pm Seward Park High School 350 Grand Street, 4th […]

Weekly Construction Updates: Oct 24th-29th 2016

Posted on Oct 24, 2016

Site 1 (242 Broome Street) Site 1 will continue to take deliveries of steel from Essex Street. Flag persons will be on Essex Street directing pedestrian and vehicular traffic. Concrete will be poured on Wednesday, October 26th. Flag persons will be on Broome Street directing pedestrian and vehicular traffic. Work will continue on Saturday, October […]

Weekly Construction Updates: Oct 17th-22nd 2016

Posted on Oct 14, 2016

Site 1 (242 Broome Street) Site 1 will continue deliveries of steel from Essex Street. Flag persons will be on Essex Street directing pedestrian and vehicular traffic. Work will continue on Saturday, October 22nd from 9am to 5pm. Site 2 (115 Delancey Street) Site 2 work will continue at the core installing structural steel, rebar, forms and […]

Weekly Construction Updates: Oct 10th-15th 2016

Posted on Oct 10, 2016

Site 1 (242 Broome Street) Site 1 will continue deliveries of steel from Essex Street. Flag persons will be on Essex Street directing pedestrian and vehicular traffic. There will be a street closure on Broome street for a concrete pour on Wednesday, October 12th.  Trucks will be staging on Broome Street between Ludlow and Allen […]