Weekly Construction Updates: Feb 6th-11th

Posted on Feb 3, 2017

Site 1 (242 Broome Street) Site 1 will be pouring concrete on Monday, February 6th. Concrete trucks will be staged on Broome Street. A crane will be on Essex Street all week. Curtainwall deliveries will occur throughout the week on Broome Street. Flag persons will be placed on Essex and Broome Street directing traffic and […]

Weekly Construction Updates: Jan 30th-Feb 4th

Posted on Jan 31, 2017

Site 1 (242 Broome Street) Site 1 will be pouring concrete on Wednesday, February 1st. Concrete trucks will be staged on Broome Street. A crane will be on Essex Street all week. Curtainwall deliveries will occur throughout the week on Broome Street. Flag persons will be placed on Essex and Broome Street directing traffic and […]

Weekly Construction Updates: Jan 23rd-28th

Posted on Jan 23, 2017

Site 1 (242 Broome Street) Site 1 will be pouring the 8th floor on Thursday, January 26th. Concrete pumps and trucks will be staged on Broome Street. Window deliveries will occur on Monday, January 23rd and Wednesday, January 25th along with miscellaneous deliveries throughout the week.  A crane is located on Essex Street. Flag persons […]

Weekly Construction Updates: Jan 16th-21st

Posted on Jan 13, 2017

Site 1 (242 Broome Street) Site 1 will continue to receive steel deliveries on Essex Street. A concrete pour for the 8th floor is expected towards the end of the week. Curtain wall deliveries are expected on Thursday, January 19th. A crane may be delivered on Essex this week. Flag persons will direct pedestrian and vehicles. Work is anticipated […]

Weekly Construction Updates: Jan 9th-14th

Posted on Jan 6, 2017

Site 1 (242 Broome Street) Site 1 will continue pouring the 7th floor slab on Thursday, January 12th with the pump truck located on Broome Street. A crane will be located on Essex Street. Flag persons will be on Broome Street and Essex Street directing traffic and pedestrians. Work may occur on Saturday, January 14th. […]

Weekly Construction Updates: Jan 2nd-7th

Posted on Jan 3, 2017

Site 1 (242 Broome Street) Superstructure work continues at Site 1.  A partial road closure of Essex Street between Broome and Delancey is expected to remove a crane from the site beginning at 10pm on Wednesday, January 4th through 6am on Thursday, January 5th.  A concrete pour for the 6th floor is anticipated to occur […]

Weekly Construction Updates: Dec 26th-31st

Posted on Dec 23, 2016

Site 1 (242 Broome Street) Superstructure work continues at Site 1. A concrete pour is anticipated on Wednesday, December 28th. Flag persons will be directing pedestrians and vehicles. There will be no steel deliveries this week. No after-hours work is anticipated.  Site 2 (115 Delancey Street) Site 2 will continue installing structural steel through the cellar and level […]

Weekly Construction Updates: Dec 19-24th

Posted on Dec 16, 2016

Site 1 (242 Broome Street) Superstructure work continues at Site 1. On Tuesday, December 20th a crane will be erected on Essex Street. Crane operations will occur from 10 pm to 6 am Wednesday morning.  Traffic will remain flowing in both directions, but limited to one lane. Flag persons will be present to direct pedestrian and […]

Weekly Construction Updates: Dec 12-17th

Posted on Dec 9, 2016

Site 1 (242 Broome Street) This week Site 1 is expected to mobilize a crane on Broome Street between Ludlow and Essex on Monday, December 12th. Traffic will be able to flow as per the DOT approved plan.  The team will rework the perimeter fence on Broome Street to allow the crane to advance concrete […]

NY1 Profiles The Market Line at Essex Crossing

Posted on Dec 9, 2016

NY1’s Michael Scotto profiles The Market Line and the new Essex Street Market opening in 2018.