Site 1 (242 Broome Street) Site 1 will be pouring concrete on Wednesday, March 29th on Broome Street. A crane will be on Broome Street Monday, March 27th, Tuesday, March 28th and Friday, March 31st. Curtainwall deliveries will arrive on Broome Street on Monday, March 27th and Tuesday, March 28th. A crane will be on Essex […]

Weekly Construction Updates: Mar 20-25th

Posted on Mar 17, 2017

Site 1 (242 Broome Street) The Site 1 crane is expected to return to Essex street at some point this week. A crane will be on Broome Street Monday, March 20th and Tuesday, March 21st. A concrete pour for the 15th floor is anticipated on Thursday, March 23rd. Curtainwall deliveries will occur on March 20th […]

Weekly Construction Updates: Mar 13-18th

Posted on Mar 10, 2017

Site 1 (242 Broome Street) At Site 1 the crane will be operating on Essex Street mid-week. The crane on Broome Street will be running Monday, March 13th, Wednesday, March 15th and Thursday, March 16th. A concrete pour for the 14th floor is anticipated on Tuesday, March 14th. Work will continue on Saturday, March 18th. […]

Weekly Construction Updates: Mar 6th-11th

Posted on Mar 6, 2017

Site 1 (242 Broome Street) Site 1 will have the crane returning on Essex Street throughout the week. A concrete pour for multiple floors of the steel structure will occur on Saturday, March 4th; the 13th floor is anticipated for Wednesday, March 8th. On March 4th and 6th there will be a crane in operation […]

Essex Crossing Site 5 Affordable Housing Lottery is Now Open!

Posted on Mar 2, 2017

Essex Crossing Site 5 Affordable Housing Lottery Now Open 145 Clinton Street The first affordable housing lottery at Essex Crossing has commenced and will be open for 60 days.  The 15-story building at 145 Clinton Street, known as Site 5, will contain a total of 211 residential units.  104 of these unit units are available […]

Community Information Session on Affordable Housing at Essex Crossing, March 6th

Posted on Mar 1, 2017

Community Information Session on Affordable Housing at Essex Crossing Monday, March 6th 6:30-8pm Seward Park High School Auditorium, 350 Grand Street PLEASE NOTE:  APPLICATIONS WILL NOT BE DISTRIBUTED AT THIS EVENT Delancey Street Associates, the New York City Department of Housing Preservation and Development (HPD) and Housing Development Corporation (HDC) will hold an Information Session […]

Weekly Construction Updates: Feb 27th-Mar 4th

Posted on Feb 24, 2017

Site 1 (242 Broome Street) Site 1 will have the crane return to Essex Street this Wednesday, March 1st. A concrete pour for the 11th floor is anticipated on Monday, February 27th. Curtainwall deliveries will occur throughout the week. Pedestrian Guards will be on site at crosswalks during deliveries. Work will continue on Saturday, March […]

Weekly Construction Updates: Feb 20th-25th

Posted on Feb 17, 2017

Site 1 (242 Broome Street) Site 1 will continue to pour concrete on Tuesday, February 21st. Curtainwall deliveries will enter the site on Broome Street throughout the week. Crane will be on Essex Street throughout the week for steel deliveries. Flag persons will be provided on Essex Street and Broome Street as needed for pedestrian […]

Construction Job Recruitment Event- This Wednesday, February 15th

Posted on Feb 13, 2017

Wednesday, February 15th 10 am – 2 pm Henry Street Settlement, 99 Essex Street Learn more about upcoming construction career opportunities.   Workforce1 will conduct onsite interviews for candidates with construction experience in the following trades: General Labor Concrete Labor Masonry Carpentry   For more information, contact Workforce1   More about our workforce partners: The Lower […]

Weekly Construction Updates: Feb 13th-18th

Posted on Feb 13, 2017

Site 1 (242 Broome Street) Site 1 will be pouring concrete on Wednesday, February 15th. Concrete trucks will be staged on Broome Street. Our Crane will be on Essex Street all week. Curtainwall delivers will be throughout the week on Broome Street. Flag persons will be placed on Essex and Broome Street directing traffic and […]