WEEKLY UPDATES

Week of June 26th-July 1st

Site 1 (242 Broome Street)

Site 1 will have no street work for the next week. Fit out work for the interior of the residential building from the 3rd floor through the 11th floor is on-going.  Work will occur on Saturday, July 1st.
  

Site 2 (115 Delancey Street)

Site 2 has concrete pours tentatively scheduled for Tuesday, June 27th and Thursday, June 29th.  Spray fireproofing will continue at the 2nd through 6th floor.  Mechanical, electrical and plumbing work will continue throughout the sub-cellar, cellar and ground floors. Installation of masonry block and door frames will continue at the cellar through 2nd floor. Installation of exterior wall panels will continue and over-sized deliveries will occur sporadically throughout the week. Deliveries may occur in the early morning hours. Flag persons will direct deliveries into the site. The hoist on Delancey Street is operational and will be jumped sporadically to keep pace with the vertical construction of the building. Back-fill and waterproofing operations will continue on the south and west sides of site.   Work will continue Saturday, July 1st.   Installation of the ConEd vaults will continue throughout the week.   

 

Site 5 (145 Clinton Street)

The upcoming week's work at Site 5 includes façade storefront installation is ongoing on the north façade, residential lobby, and Clinton street.  Rebar and formwork installation on Broome Street park. Miscellaneous carpentry, plumbing, and electrical work is ongoing from cellar through 15th floor. Cabinetry installation continues on 8-10th floors. Remaining sub-frame and window installation from 8th-11th floors is ongoing. Façade metal panel installation ongoing on 11th-12th floors, as well as scaffold removal on tower is ongoing from 13th floor down. ConEd vault transformers have been placed and interconnection work will be ongoing for this next week. Elevator installation work continues for freight, service, and passenger elevators.  General construction work will occur on Saturday, July 1st from 9am to 5pm.    

 

Site 6 (175 Delancey Street)

The coming week's activity at Site 6 includes storefront installation at the 1st  floor Broome and Delancey Street elevations. Interior framing, drywall, mechanical, electrical, and plumbing work continues from the cellar to the 14th floor. Roofing work will continue on the 4th and 5th floor terraces. Work will continue on Saturday, July 1st from 9am-5pm.