WEEKLY UPDATES

Week of August 14th - 19th

Site 1 (242 Broome Street)

Site 1 will continue with interior fit out work. Verizon will be excavating on Broome Street throughout the week. Two lanes of traffic will be open for cars and pedestrians. Flag persons will be directing traffic as needed. Deliveries will be taken on Broome Street as well, throughout the week. Work will continue on Saturday, August 19th.  

  

Site 2 (115 Delancey Street)

Site 2's superstructure concrete program will continue for the next few months. Concrete pours are scheduled for Wednesday, August 16th and may run into the evening hours as permitted. Interior mechanical, electrical and plumbing (MEP) fit-out will continue in cellar through 6th floor and MEP risers will begin to be installed through the 8th floor. Spray fire-proofing, paint and masonry will continue throughout floors 1 - 7. Interior framing layout will begin next week on the 7th and 8th floor and continue its way up the building. UPDATE: The site will be open both Saturday and Sunday, August 19th & 20th. Saturday will be a typical light day of construction with miscellaneous trades. We will be working Sunday to install an escalator that requires the construction hoist to be out of operation for the day’s work.

  

Site 5 (145 Clinton Street)

The upcoming week's work at Site 5 includes façade storefront and glass installation at residential lobby, and Clinton Street; rebar, formwork, and concrete work, 3rd floor terrace, perimeter wall finish framing, insulation, and heating and air conditioning system installation. Final sheet rocking is ongoing from 3rd-12th floors. Cabinetry installation continues on 14th-15th floors. Façade metal panel installation is on-going on  6th-7th floors, as well as scaffold removal. ConEd work continues within site. Elevator installation work continues for freight, service, and passenger elevators General construction work will occur on Saturday,   August 19th from 9am to 5pm.         

 

Site 6 (175 Delancey Street)

The coming week's activity at Site 6 includes sidewalk concrete work on Clinton Street.  Storefront work will continue on Broome Street. ConEd will complete work at electric vaults on Broome Street. Landscape planting at 4th and 5th floor roof gardens will be ongoing.  Interior finish work continues at the residential tower.  Framing, sheetrock, and mechanical, electrical and plumbing (MEP) work is ongoing on commercial podium floors. Work will continue on Saturday, August 19th.