Weekly Construction Updates: Sept 26th-Oct 1st 2016

Posted on Sep 26, 2016

Site 1 (242 Broome Street) Site 1 will continue erecting steel from Essex Street. Flag persons will be on Essex Street directing pedestrian and vehicular traffic.  No after-hours work is anticipated. Site 2 (115 Delancey Street) Site 2 work will continue at the cellar level with the installation of pile caps, waterproofing, cellar foundation walls […]

Weekly Construction Updates: Sept 19-24th 2016

Posted on Sep 19, 2016

Site 1 (242 Broome Street) This week Site 1 will be erecting steel from the Essex Street side beginning on Monday, September 19th and continuing for the next 8 weeks. Flag persons will be on Essex Street directing pedestrian and vehicular traffic. UPDATE: Work may occur on Saturday, September 24th from 9am-5pm. Site 2 (115 […]

Weekly Construction Updates: Sept 12-17th 2016

Posted on Sep 9, 2016

Site 1 (242 Broome Street) Site 1 will be pouring concrete for part of the mud slab either Tuesday, September 13th or Wednesday, September 14th. Deliveries for the steel superstructure will start this week.  Flag persons will be staged on Ludlow Street and Broome Street directing pedestrians and vehicles during deliveries. No after-hours work is […]

Weekly Construction Updates: Sept 5th-10th 2016

Posted on Sep 2, 2016

Site 1 (242 Broome Street) Site 1 will be pouring concrete the morning of Tuesday, September 6th for the north foundation wall.  Concrete trucks will be staged on Broome Street. A partial closure of Essex Street is anticipated to begin on Saturday, September, 10th at 10pm through Sunday, September 11th at 10am to accommodate crane placement […]