Weekly Construction Updates: March 28th-Apr 2nd 2016

Posted on Mar 28, 2016

Site 1 (242 Broome Street) This week Site 1 will be placing the concrete mud slab and installing rebar for the mat slab, in addition to exporting soil. The concrete trucks and concrete pump will be located within the site. The drill rig will also be located within the site gate. Flag persons will be […]

Weekly Construction Updates: March 21st-26th 2016

Posted on Mar 21, 2016

Site 1 (242 Broome Street) This week Site 1 will placing the concrete mud slab. The concrete trucks and concrete pump will be located within the site. Drilling will begin for the sleeve for the elevator piston. The drill rig will also be located within the site gate. Flag persons will be positioned at the […]

Free Event: The History and Future of Markets in NYC, March 20th

Posted on Mar 14, 2016

The History and Future of Markets in NYC (Part Two): Sunday, March 20th, 12-1pm at the Lowline Lab Delight your inner foodie with stuffed risotto balls and other light bites as we discuss the importance of preserving the rich history of markets in New York City. Moderated by local history mavens, the Bowery Boys, alongside […]

Weekly Construction Updates: Mar 14th-19th 2016

Posted on Mar 14, 2016

Site 1 (242 Broome Street) This week Site 1 will be placing the concrete mud slab. The concrete trucks and concrete pump will be located within the site. Drilling will begin for the sleeve for the elevator piston. The drill rig will also be located within the site gate. Flag persons will be positioned at […]

Weekly Construction Updates: Mar 7th-12th 2016

Posted on Mar 8, 2016

Site 1 (242 Broome Street) Concrete placement will be conducted on site, no pump will be required. Flaggers will direct pedestrian and vehicular traffic as needed along Ludlow and Broome. No after-hours work is anticipated. Site 2 (115 Delancey Street) Site 2 will continue excavation and support of excavation at the cellar and sub-cellar level. Sub-cellar […]

Weekly Construction Updates: Feb 29th-Mar 5th 2016

Posted on Mar 8, 2016

Site 1 (242 Broome Street) Site 1 will be grading and exporting soil in preparation for mud slab installation which is anticipated to be placed on or about Thursday, March 3rd. Concrete trucks will enter site at the corner of Broome and Ludlow. Flaggers will be directing vehicular and pedestrian traffic along Ludlow and Broome. […]

Weekly Construction Updates: Feb 22nd-27th 2016

Posted on Mar 8, 2016

Site 1 (242 Broome Street) This week, Site 1 activities include excavation for exporting soil off site and concrete placement for the support of excavation. No after-hours work is scheduled. Site 2 (115 Delancey Street) Site 2 will continue excavation and support of the cellar and sub-cellar. Sub-cellar concrete pile cap installation will begin this week. Excavation […]